Supreme Site Services v Shape: Advocate General ØE on Brussels Ia’s scope of application (‘civil and commercial’ in light of claimed immunity. Opinion at odds with CJEU in Eurocontrol.

Update 12 June 2020 Maria has further analysis here.

Many thanks again María Barral for continuing her updates on C-186/19 Supreme Site Services v Shape, on which I reported earlier here and here; see her summary of Thursday’s opinion of the AG below. I just wanted to add two things.

Firstly, the AG’s suggestion that in spite of the intervening Court of Appeal judgment which would seem to make the CJEU case nugatory, the case should continue for against the appeal’s court decision, a further appeal is underway with the Supreme Court.

Second, at 93 etc. the AG advises that the immunity or not of the defendant, bears no relevance to the scope of application of BIa for it does not feature in the concept of ‘civil and commercial’ as developed by the Court.

That in my view is at odds with the CJEU’s very statement in Eurocontrol, at 4: the Court’s seminal judgment on civil and commercial itself in so many words links the scope of application to the practicality of recognition: in Eurocontrol the CJEU interprets ‘civil and commercial’ ‘in particular for the purpose of applying the provisions of Title III of the Convention‘: there is little use bringing issues within the scope of the Convention and now BIa, if ab initio there is no prospect of recognition and enforcement.

In other words I am not at all sure the Court will follow the AG on that part of the analysis. I should emphasise this is my view: María’s review independent of that follows below.

Geert.

 

Immunity does not impact jurisdiction based on Regulation Brussels I bis, AG Saugmandsgaard Øe dixit

María Barral Martínez

Following up on the previous posts (see here and here) discussing the contractual dispute between Supreme site Services v. SHAPE, today’s post addresses  the Opinion of Advocate General Saugmandsgaard Øe in C-186/19 Supreme v Shape.

While the questions posed by the referring court concerned the interpretation of articles 1(1) and 24(5) Brussels Ia, ‘at the CJEU’s request’ (5) limits his analysis to Article 1(1).

In a nutshell, the analysis in his Opinion is twofold: on the one hand, he examines whether the action brought by SHAPE – an international organisation- seeking the lift of an interim garnishee order falls within the meaning of “civil and commercial matters” laid down in article 1(1) of the Brussels I bis Regulation. On the other hand, he analyses whether the fact that SHAPE had invoked its immunity from execution in the interim relief proceedings has any significance on the above evaluation.

In tackling the first prong of his analysis, AG Saugmandsgaard Øe recalls the public hearing held at the CJEU back in December 2019. There, the focus was put on how the  “civil and commercial” nature of the interim relief measures sought by SHAPE is to be assessed – in the light of the features of the proceedings on the merits, based exclusively on the interim relief proceedings or only in relation to the nature of the rights the interim measures intend to safeguard matters. AG Saugmandsgaard Øe rejects the first two alternatives and follows the thesis supported by the Governments of The Netherlands and Belgium and by the European Commission: in line with the judgments de Cavel I and de Cavel II, the nature of the rights whose recognition is sought in the proceedings on the merits and whose protection is the purpose of the interim or protective measures sought is decisive. (Point 46 and 51)

Furthermore, AG conducts a thorough analysis on the immunities recognised under Public International Law vis-à-vis the application of Brussels Ia. He argues that to determine whether a dispute should be excluded from the scope of BIa on the grounds that it concerns “acts or … omissions in the exercise of State authority” – A1(1) in fine-, it is necessary to assess whether the action is based on a right which has its source in acta iure imperii or in a legal relationship defined by an exercise of State authority. (at 90)

On that basis, he concludes that an action for interim measures such as the one in the present case, seeking the lift of a garnishee order, must be regarded as “civil and commercial” in so far as the garnishee order was aimed to safeguard a right arising from a contractual legal relationship which is not determined by an exercise of State authority. (at 104)

Finally, AG Saugmandsgaard Øe posits that the fact that an international organization as SHAPE has invoked immunity from execution, has no bearing in the assessment of the material application of Brussels Ia. What’s more, it cannot serve as an obstacle for a national court to establish its international jurisdiction based on the aforementioned Regulation.

(Handbook of) EU private international law, 2nd ed. 2016, Chapter 2, Heading 2.2.2.2.

2 Replies to “Supreme Site Services v Shape: Advocate General ØE on Brussels Ia’s scope of application (‘civil and commercial’ in light of claimed immunity. Opinion at odds with CJEU in Eurocontrol.”